What Does a Hold-Point Waterproofing Inspection Show When There's More Than One Membrane?

Written by Kevin Ly

The short answer

An inspection records what can be seen on the day. On a floor with more than one membrane, an inspector called in after the top membrane, before tiling, sees the top membrane only. For every membrane under it, and anything else under a bed or screed, the inspector has only what they're given, photos and paperwork, not what they saw. If you want every layer on the record, book an inspection before each one is covered, or agree on the photos before work starts.

What a floor with more than one membrane looks like

The build-ups vary. The basic one is a membrane on the slab, a tile bed or screed over it, and another membrane on top. Some have an acoustic layer, either under the first membrane or between two of them. Some have three membrane layers.

AS 3740, the standard for waterproofing domestic wet areas, allows the membrane to go either above or below a tile bed or screed (cl 4.2).

For apartments, the NCC 2022 Deemed-to-Satisfy route (Volume One, F2D2) has wet areas meet Specification 26 and AS 3740.

What can be seen at each stage

Each layer can only be inspected while it's the top one. Here is what an inspector can see, depending on when they're called in:

What an inspection of the top membrane does show

Called in after the top membrane, I can record:

On any floor with more than one membrane, ask which membrane is connected to the floor waste.

What it can't show

From the top membrane, an inspection can't show:

Photos and data sheets: what they can stand in for

When I'm called in after the top membrane, I'm usually handed photos of the lower layers, from the waterproofer, the builder or the owner. Sometimes there are none at all.

The photos most useful to me show three things:

Data sheets are important too, and I'm rarely given them. Most of the time I find them myself, which I can only do if I know which product went on each layer. A data sheet says what a product is made for. It doesn't say what was done on your floor.

In the report I keep what I saw myself separate from what I was given.

If you want every layer on the record

There are two ways to do it:

  1. Book an inspection at each stage: after each membrane, before anything goes over it.
  2. Agree a photo list with the builder before work starts.

A short list you can forward to the builder:

Whether a membrane can be covered by another layer in your system

That depends on the membrane system. Some are designed to be covered and some aren't. Ask for the manufacturer's written build-up. This page doesn't rule on any product.

What the report is, and isn't

The report is a record of what was seen and measured on the day. It isn't a certificate. Whether the work complies is for your certifier or engineer to decide.

Next step

Send us the scope and the builder's program before the first membrane goes on, and we'll tell you which stages can be inspected. If you're on a strata committee, see how a committee gets an inspection approved. For a single stage, see what a pre-tile inspection covers.